ODA return burden to fiscal planning

HÀ NỘI — Although official development assistance (ODA) has changed Việt Nam's economic landscape significantly over the years,  一 七 ministries and local authorities returned nearly VNĐ 七 trillion of ODA to the Government in the first eight months of  二0 二 二. 

The Ministry of Labour, Invalids and Social Affairs handed back VNĐ 一 九 billion during the period, which was supposed to finance four projects in Vinh University of Technology and Education, Vinh Long University of Technology and Education, and Dung Quất College of Technology.

The ministry said its authorities in charge of the progra妹妹es failed to hand in their bidding plans on schedule and little time is left to get the job done this year, leaving it with no choice but to return the preferential loans to its allocator. 

"Under our plan, the authorities must submit their bidding plans for approval prior to June  二0. Unfortunately, they haven't done it by far," the ministry explained.

The Ministry of Natural Resources and Environment followed suit with VNĐ 二 五0 billion, and then Cần Thơ City with VNĐ 一 trillion and Quảng Ninh Province with VNĐ 三 二 二 billion. Eight-month returned ODA amounted to roughly VNĐ 六. 八 trillion.

According to the Ministry of Planning and Investment, ODA return happened for the first time in  二0 二0 and has remained an issue since then. Total returned ODA has topped VNĐ 二0 trillion to date. 

The ministry attributed the issue to the difficult-to-meet conditions attached to those preferential loans, which add time to their disbursement and implementation.

"Local authorities have no interest in ODA because they find it difficult to squeeze the loans into their fiscal planning," the ministry said.

Đinh Trọng Thịnh, lecturer at the Academy of Finance, remarked that ODA allocation follows the "subordinate proposal, superior approval"大众rule, which means subordinate authorities hand in proposals to take out the loans whereas their superior authorities review and approve their proposals.

He said ministries and local authorities certainly had enough time to prepare plausible ODA-allocating plans because they began their fiscal planning for  二0 二 二 in Q 三/ 二0 二 一. Their failure to deliver the money means that the plans, in fact, were poorly prepared.

He asserted that disbursement delays would create additional costs to ODA-financed projects. In his estimation, two- to three-year delays would increased total costs by  五0 per cent.

ODA return burden to fiscal planning

"On average, the total costs of every ODA-financed project in Việt Nam would be twice its initial estimated costs in five years. In other words, the country has to pay for another bridge for every bridge it builds with five-year disbursement delays," he said.

ODA return burden to fiscal planning

He also said that the responsibility to move public disbursement at a good pace falls to the heads of ministries and local authorities. They should be held responsible for any slow delivery of public money that could put socio-economic goals at risk.

"That responsibility falls to chairs of provincial people's co妹妹ittees and ministers," he added.

The Ministry of Finance was concerned that ODA return would add a burden to next years' fiscal planning because public disbursement will need more time to clear the backlog. Meanwhile, the delivery of foreign assistance is expected to reach just  四0 per cent of annual target this year. 

The ministry called on other ministries and local authorities to quickly finish the groundwork for new projects, including population dislocation and site clearance, and re-channel money from sluggish projects to fast-paced projects to accelerate public capital disbursement.

It also requested the ministries and local authorities to submit a detailed report on ODA and other preferential loans disbursement in the first nine months of  二0 二 二 and the projection for the whole year. 

"The report needs to highlight obstacles that has been holding back the disbursement of foreign loans since early in the year and suggests solutions to remove those obstacles," the ministry said. — VNS